What is the Bracket installation order of the DVLED Floor Stand configuration?

The Bracket installation order varies from the Wall-mount configuration. Please follow the steps in the respective order for the Floor Stand configuration:

  1. Bottom cross beam installed to the left and right supports.
  2. Top cross beam installed to the left and right supports.
  3. Original mounting bracket removed from the top and reattached to the middle of the cabinet. Screw holes on the TOP of the bracket when installed.


Please move on to install the System Control Box first before installing the Cabinets


For bracket installation order of the Wall-mount configuration, please click here. 



Recommended Links

"How do I install a DVLED display with a Floor Stand configuration?"

Ostatnio zmodyfikowano: kwi 2022

Direct View LED Display Wsparcie

General Questions

Skontaktuj się z nami

Skontaktuj się z nami bezpośrednio jeśli nie możesz uzyskać odpowiedzi i rozwiązań dla swoich produktów ViewSonic