What is the System Control Box installation order of DVLED Displays?

The System Control Box installation order is the same for the Wall-mount and Floor Stand configuration. Please follow the steps in the respective order for the System Control Box installation order:

  1. Seven system control box attachment points screwed down

    Control box Power cables:

    - Running from the back of the control box?

    - Running from the bottom of the control box?

  2. Control box placed underneath the cabinets and used screws to secure the box to the cabinets

  3. Five sets of Ethernet and Power cables passed through the holes in the cabinets and connected to the cabinets

  4. Ensured control box is connected to each cabinet

  5. Attached control box’s Power cable to the power button

  6. Installed control box cover using supplied screws



Recommended Links

"How do I install a DVLED display with a Floor Stand configuration?"

"How do I install a DVLED display with a Wall-mount configuration?"


Ostatnio zmodyfikowano: kwi 2022

Direct View LED Display Wsparcie

General Questions

Skontaktuj się z nami

Skontaktuj się z nami bezpośrednio jeśli nie możesz uzyskać odpowiedzi i rozwiązań dla swoich produktów ViewSonic