Wall-mount - Upper and lower bracket locations aligned and mounted first
- Upper bracket screw holes on the bottom
- Cabinets are installed before system control box is installed
- After upper and lower brackets installed, Cabinet "C" installed in the center position first.
- Next, Cabinets "B", "D", "E", "A" installed in this respective order
| Floor-stand - Bottom cross beam attached to left-right supports, then top cross beam
- Relocate original mounting bracket from the top to the middle. Mounting bracket screw holes on top
- System control box installed before cabinets are installed
- After upper and lower brackets installed, Cabinet "B" installed just left of the center-position first.
- Next, Cabinets "B", "D", "E", "A" installed in this respective order
|